|
5
Development of Preferred Route
5.2
Northern Assessment
Results
of Assessments
A formalised process was applied to the evaluation process which
is documented in Chapter 17 of Volume 2 and summarised in the Impact
Matrices, RSR2 figures 17.1 to17.4 and the Selection Matrices shown
in tables 17.1 to 17.8 of Volume 2. These steps are summarised below
together with the results of each evaluation.
Step 1: The engineering and environmental effects of each
route corridor within each Section A to D were recorded on an Impact
Matrix. Also lengths of route where the route corridor could be
modified to overcome major impacts were identified. Impact Matrices
for Section A to D are shown in RSR2 figures 17.1 to 17.4.
The route options were compared under the following headings: -
- Impacts
on People
- Flora, Fauna
and Fisheries
- Archaeology
and Cultural Heritage
- Agricultural
Land Use
- Landscape
and Visual
- Engineering
- Geology and
Hydrogeology
Step
2: Where alternative routes started and finished at common points
within a single Section, the two route corridors were compared using
a summary Selection Matrix and the less favourable route corridor
discarded.
As a result, Route A3 was discarded in view of its greater impact
on people. Route A4 was discarded because of its ecological and
landscape impacts near Calberstown and the impact on a major pig
unit at Kilgowan.
Overall Route D3 was seen to have advantages compared with Route
D5 particularly in relation to the crossing of the River Barrow.
Hence Route D5 was discarded from further considerations.
Step 3: Matrices for the main Traffic/Cost-Benefit/Socio-Economic
Impacts were prepared for a number of representative overall Route
Options (Route 1, 2, 3, 4 and 7) see table 17.9 of Volume 2. Those
route options which were deemed to be less favourable were discarded
from further evaluation.
Consideration of the traffic issues indicated that routes to the
east of Carlow were preferred. Excellent access to Carlow Town could
be provided via junctions on the existing N9 to the north and south
of the town. With routes to the west of Carlow, traffic volumes
entering Carlow Town from the west increased significantly compared
with the do-nothing situation. Traffic would have to cross the town
to reach the industrial/commercial developments which are predominantly
on the east side of the town.
The Present Value of Benefits was higher for the routes to the east
of Carlow. As the capital costs of all routes were similar, these
routes also showed higher Benefit to Cost Ratios.
In socio-economic terms the favoured route was via Athy and east
of Carlow as it best served Athy and provided excellent access to
Carlow Town. The issues summarised above, together with consideration
of the engineering and environmental impact of Route C4 west of
Carlow, led to the conclusion to discard route options to the west
of Carlow Town. This decision reduced the number of possible route
options significantly and, in the next step, the remaining route
options were compared on a section by section basis.
Step 4: Selection matrices were drawn
up for the remaining route corridors in each section. These are
shown in tables 17.4 to 17.7 of Volume 2.
From Step 4, Route C6 at Carlow emerged clearly as the Preferred
Route when compared with Routes C3 and C5. Route C6 directly affected
significantly fewer properties and also had fewer people within
the 300 metre corridor each side of the route centreline. Route
C6 had significant advantages in engineering terms in that it has
the best earthwork balance. Further the route is preferred in hydrogeological
terms in that it does not cross any reported groundwater resources,
whereas Routes C3 and C5 cross major gravel acquifers between Maganey
and Knockarda and south of Newtownallen respectively.
With Route C6 selected, the choice north of Carlow was thus reduced
to Route A1 plus B3 or Route A5 plus B5 and these routes were evaluated
further as Route 9 and Route 10.
Step 5: Selection matrices were prepared
for the remaining overall Route Options (Routes 9 and 10) together
with Traffic/Cost-Benefit/Socio-Economic Impacts see RSR2 figure
17.5 and table 17.10 of Volume 2. This enabled a Preferred Route
from Kilcullen to south of Carlow to be identified.
The Routes 9 and 10 were identical south of Carlow and were tested
to assess the advantages and disadvantages of a route following
the N9 corridor (Route 9) or going via Athy (Route 10). Route 9
included as part of the scheme, the cost of a high standard single
carriageway link from the N9/N10 scheme to Athy with a connection
eastwards to the R747 near Ballitore. In environmental and engineering
terms the analysis showed that the differences between the two routes
were generally not significant.
The traffic and cost-benefit analysis showed that volume of traffic
attracted to Route 10 was marginally higher than to Route 9. However
the discounted travel and accident benefits were significantly higher
for Route 9 than for Route 10. This is due to the extra distance
traffic has to travel between Carlow and Kilcullen using Route 10
via Athy. It results in a reduction of the Benefit to Cost Ratio
from 2.01 to 1.66.
In socio-economic terms it was concluded that, with the high standard
Athy to R747 Link Road, Route 9 would bring major socio-economic
benefits to Athy. Route 9 would provide most of the benefits that
would accrue from implementation of Route 10.
Based on this analysis, Route 9 was selected as the draft Preferred
Route because of its significantly better economic performance compared
with Route 10.
Step 6: Selection matrices for the
remaining combination of routes in Selection D were prepared for
those options which connected to Route Corridor E1 which was the
emerging Preferred Route Corridor in the southern section of the
study area.
South of Carlow Route D3 affected less properties than Route D4
and was selected. As Route E1 was emerging as the Preferred Route
south of Paulstown, see Volume 3, a final comparison was completed
and is shown in table 17.8 of Volume 2. This compared a new connector
between Route D3/D2 and Route D4 (i.e. via node 33) with an alternative
route using the E1/E6 connector (i.e. via node 36). The comparison
showed that the route via node 33 had less impact in terms of properties
affected and was chosen in preference to the route using connector
E1/E6.
Step 7: Where possible the draft Preferred
Route Corridor was adjusted to reduce the impacts further. Preliminary
junction locations and layouts further. Preliminary junction locations
and layouts were developed and link roads were included.
The draft Preferred Route Corridor was adjusted in four main locations
prior to the Preferred Route being exhibited at Public Consultation
No. 3. The amendments were made primarily to reduce the impacts
on residential and other property following examination of available
material from Public Consultation No. 2 and extensive site visits.
The main four locations were:
- Crookstown
Lower to Belan
- Belan to
Prumpelstown
- Bennekerry
to Tinryland
- Clonmelsh
to Powerstown
Athy
to R747 Link Road
As described earlier a high quality link road was included in the
draft Preferred Route to improve, significantly, the standard of
road connections between Athy and the National Primary Road Network.
Four options for the alignment of the Link Road were investigated
and an option selected which avoided demolition for properties and
reduced farm severance by adopting an 1.8km length on the existing
Country Road.
|
|